Building Central Asia's
first Tier IV data fortress.
We update the world on every phase — from foundation to certification. 11 hectares of purpose-built infrastructure under construction in Astana.
Foundation complete. First buildings rising. 61% of capacity reserved pre-launch.
- Campus area
- 11 hectares
- Total build area
- 60,000 m²
- DC buildings
- 4
- IT load (phase 1)
- 28 MW
- First-phase launch
- Q1 2026
- Pre-launch reservation
- 61%
Project timeline
- Oct 2025
Land preparation complete
Site grading, access roads, and utility tie-ins finalized on the 11-hectare Astana campus.
- Nov 2025
Foundation poured
Reinforced concrete foundation laid for the first DC building.
- Dec 2025
Structural erection
Primary structural steel and envelope going up on building 1.
- Jan 2026
MEP rough-in
Cooling headers, power distribution, and fire suppression being installed.
- Q1 2026
First phase soft-launch
Initial server halls handover to anchor tenants. Phase 1 commissioning.
- Q3 2026
Uptime Institute audit
Tier IV certification process begins.
- 2027+
Expansion to 100 MW
Additional DC buildings come online. Full 4,224-rack capacity.